top of page

PROGRESS

02.jpg
iz-ceste.jpg

2009

Started  planning for future of this site.

2014 

Zoning permission granted.

2019

Registered as building site.

2022 Remove existing property

2011

Plan completed and church agreed.

2016 Building permit granted, communal tax paid.

2021 

Preparing contract with construction co.

Information on major points of progress during this project

  • We began examining our options for the existing building in 2008/2009. It was apparent that it needed a new roof, completely new electricity, new plumbing, and new central heating. In addition, the building only accommodates approximately 90 seats in the sanctuary, which forced us in 2014 to begin holding two services each Sunday morning to have enough space for everyone. Now we are even facing challenges with space in our second service.​​

  • Our initial intent was to extend the existing building; however, because of town planning, the building needed to be moved back 2.5m to allow for potential road expansion, which would not be possible with the existing sanctuary. It was apparent that there were only two options: (1) sell the current property and purchase another site, or (2) demolish and rebuild 2.5 meters back.​

  • In 2011, the plan was completed and approved by the church members. We then had to complete all the planning processes and obtain zoning permission, permission from neighbors, and other necessary consents. Building permission was finally received in March of 2016.​

  • After many meetings with the local governmental authorities, our project manager, our construction company, and church members, we agreed to register the property as a "building site in preparation" in April of 2019. We were given one year to prepare the site, and construction is planned to begin in March of 2020.  ​

We would kindly ask you to consider joining us in this project.

zgradba-logo-copy.jpg

Getting ready to say goodbye to the old building, it has serviced us so well, there are so many memories.

Temp%20facility_edited.jpg
Temp Facility 3.jpg
Temp Facility 4.jpg
Temp facility 2.jpg

Temporary facility (43 Celovška) found, rented (Dec. 2020), and renovated, ready for first services after Covid-19 restrictions.

01.jpg

Expected to break ground March 2021.

int03.jpg
bottom of page